Scheduling & Sequencing · Module 2 of 4
Two Machines in a Row: When Sequencing Finally Moves the Finish
Last module, the batch always finished at the same hour — the order was only a fairness call. Now there are two machines in a row at Cedarline: print, then finish. The same five jobs can land at hour 28 or hour 38 depending on the order — a 10-hour swing, nothing but sequence. Johnson's rule solves it: feed the finishing station fast, drain it last, reading each job by the machine it's short on, not its size. The press was never the lever; the finishing station's idle time was.
0 of 16 items completed0%~77 min remaining
Material · 16 items